WTC Redevelopment Program Integrity Monitoring

This $16 billion program for reconstructing the World Trade Center site included the construction of the 1,776-foot-tall One World Trade Center (One WTC), the tallest building in the Western Hemisphere. The program included the construction of all the new facilities on the entire site; our services focused on 1 WTC, the 9/11 National Memorial and Museum, and the Vehicle Security Center, along with other site improvements.
The Joint Venture Integrity monitoring team consisted of inspectors, accountants, and engineering professionals. UrbanNY’s role was overseeing the engineering elements of the entire assignment to provide verification that the PANYNJ was receiving the intended value for the constructed projects.
UrbanNY, as a team member of the Fortress Monitoring Group Joint Venture, provided program management, engineering, quality, and safety services that supported the goal of delivering a professional review to PANYNJ, verifying contractor performance and project compliance, and maintaining transparency and accountability across the program. The Joint Venture conducted reviews of procedures and processes to ensure the program was delivered as intended, with minimal impact on cost, schedule, and quality, while maintaining a high degree of safety and minimizing environmental risk. The work was performed in consultation with the PANYNJ design and construction contractors and integrated with the overall program implementation. UrbanNY interfaced with PANYNJ project management, consultant project management, contractor project management, superintendents, foremen, shop stewards, and trade workers. Continuous review of and dialogue with pertinent individuals to ascertain the status of contractual and regulatory requirements, documents, and permits. Conducted site visits to compare field conditions with contractual requirements. Observed and reported findings, gaps, and actions.
Port Authority of NY and NJ